Project: Dominion Energy to assess feasibility of a solar farm on 60-80 acres of a closed landfill off Jolly Pond Road, James City County.
-
Board Vote: Approved 4-1 (Supervisor Barbara Null opposed) for a lease agreement.
-
Lease Terms:
-
1-year feasibility study period.
-
Up to 5 years for development.
-
~35-year operation with $1,000/acre lease, potentially $60,000/year for 60 acres.
-
-
Payment: Full payment starts post-feasibility confirmation.
-
Land Use: 545-acre site includes Jolly Pond Convenience Center and police shooting range, both to remain active.
-
Access: Dominion has full parcel access for testing, including capped landfill area.
-
County Oversight: Retains control over access/operations during study and development.
-
Context: Supports energy demands from data centers and other developments.
-
Other Solar Projects:
-
Operational: 20MW Hill Pleasant Farm, 20MW Norge.
-
Under review: 3MW Racefield Drive, 5MW Anderson’s Corner.
-
Approved, pending plans: 3MW Ivy Hill Road.
-
-
Permit Review: County can review and reject during special use permit process.